B12 |
Megabay 1 |
Pending scrapping? |
Cryo x2, Static fire Jul 15th. Full stack cryo tests Sep 23rd and Oct 7th. FTS installed Oct 9th. Launched as IFT-5 on Oct 13, returned to launch site for successful chopstick catch. Moved to Megabay 1 Oct 15th. |
B15-2 |
Megabay 1 |
Pending FTS install |
Stacked from July to September. Methane tank cryo test Dec 27th, full cryo test Dec 28th. Static fired Feb 9th. Launched and landed Mar 6th. Static fired Sep 7th. |
B16 |
Gulf of Mexico |
Destroyed |
Stacking completed by Dec 26th. Cryo tested Feb 28th. Static fired Jun 6th. FTS potentially installed Jun 18th. Hot staging adapter removed Jun 19th. FTS installed Aug 17th. Rolled out to launch site Aug 21st. Launched on 2025-08-26, destroyed on impact following a successful landing burn. |
B17 |
Rocket Garden |
Pending engine install |
Parts spotted. First two sections moved to Megabay 1 Jan 4th. Fully stacked by Apr 7th. Cryo tested Apr 9th. |
B18.1 / Test Tank 17 |
Massey's |
Cryo testing |
Test article for Booster v3. Parts spotted Feb 24th, Apr 21. Cryo tests start Jun 2nd and 3rd, continue until tank bursts Sep 18th. |
B18.3 |
Massey's |
Testing |
Parts spotted Aug 27th. Moved to Massey's Sep 20th. |
B18 |
Megabay 1 |
Stacking |
Parts spotted May 19th. |
B19 |
Starfactory |
Stacking |
Parts spotted Aug 11th. |
Starbase activities (2025-09-08):
Florida: